Engineering progress displayed on AGM day

On AGM day the locomotive showed off its latest additions as the build continues at a good pace. At the front end Richard Cadge, Chris Moore and Paul Johnson inspect the new lamp iron brackets and the new front foot plating.

image

image

The motion bracket was trial fitted for the day as progress towards setting the final position of the cylinders continues.

image

Bill Hall holds the newly manufactured reverser handle

image

the new Steam Fountain casting sourced by Paul Johnson goes into stores awaiting use once the boiler is refurbished