Your shopping cart is empty
Visit the shop

To securely make a donation, click on the button above, then simply follow the prompts to donate as much as you can spare to our cause via PayPal - please note you don't even need a PayPal account.

Visit us on Facebook (https://www NULL.facebook NULL.com/6880BettonGrangeSocietyLtd)

David

Work starts on the Tender

with agreement in place to hire the 4,000 gallon tender belonging to the owner of  2-8-0 No. 3814, our team started sanding down the metalwork in preparation for painting into BR Western green.

Betton Grange moves to Tyseley

On the 25th June the locomotive was transported to Tyseley in readiness for the boiler to be fitted. This should take place during the summer.  Once complete the movement back to Llangollen will be start of the work needed to finish the locomotive.

Yes we are getting very close to finishing the job. Right now we’re seeking sponsors for the Superheater elements, twenty one of each are needed to finish the boiler. See our shop page here.

photos of 6880 arriving at Tyseley where the locomotive will be on display in the workshop during this weekends Open Day.  See you there.

 

Boiler work at Tyseley nearing completion

a visit to Tyseley locomotive works a few days ago revealed the huge progress made with our boiler. The back head now complete, the new boiler ring ready to be fitted and the smoke box ring now fitted to the smoke box. All looks on course for completion as planned by the end of June.

In addition the steam fountain was nearing completion and the safety valve was being machined.

Cylinder Cleating nears Completion

work has continued on the cylinder creating which has proven to be a harder job than expected working without drawings.

however the job is nearly finished.

TENDER HIRE FROM 3814

When 6880 steams within the next 12 months it will run with a 4000 gallon Collet tender hired from 2-8-0 No. 3814. A deal has been struck with the owner of the tender to use it until such time as 3814 itelf has been overhauled. The tender is currently at Llangollen nearing the end of a restoration and will be available to us later this year.

Boiler update at Tyseley

work continues at Tyseley where the rivet holes for connecting the back plate to the foundation ring were being drilled. We also saw an unusual view of the firebox rear with both inner and outer back plates removed. The new front boiler ring has now arrived on site and is available for fitting when required.

Cylinder Draincocks Fitted

at the beginning February our team fitted the cylinder draincocks during the recent working weekend

Progress on boiler work at Tyseley

work on the boiler continues on schedule for completion this Spring. The new firebox lower outer sheets are ready to be welded in. Meanwhile two new throat plates have been made for both 4936 and 6880, ready to be riveted in once the outer sheets are finished. Outside the new smoke box barrel has arrived ready to be fitted once the new front boiler barrel arrives. Also on site is the metalwork for the new ashpan.

December Raffle Draw

the following people were winners in our raffle drawn today 10th December.

liz McGuinness will be in touch to advise the winners

 

1st David Williams £200
2nd Geoff Rogers £100
3rd Dave Gill £68.80
10 prizes of £6.80
Chris fox
Mr Frank
John McNaughton
Geoff Morris
Geoff Turner
W Mills
Steve Worrall
Michelle Pyle
R M Tucker
D Marks

Member’s Day

on 29th October the Society held the annual Member’s Day at Llangollen,

addressing the meeting was our ambassador Mark Evans visiting us to see for himself the progress on the locomotive.

work on completing the ‘bottom end’ of the locomotive continues whilst work on the boiler continues at Tyseley. The Boiler Fund has now reached the amazing total of £219,000 a remarkable achievement. Les than 10 Granges remain to be adopted raising £70,000 through this initiative.