Cab Front Sheet work

The cab front sheet is being prepared for fitting.

Here Robin Matthews uses the special drill system to line up the holes so correctly profiled bolts can be used to permanently fix it in place

Wheels now painted

Following delivery to Llangollen the wheels have now received a coating of primer, undercoat and two layers of gloss black. The finished wheels await the preparation of the axleboxes and other work before re-wheeling can take place.

WHEELS NOW RE-TYRED

The 3 wheelsets for 6880 have now been re-tyred at the South Devon Railway’s Buckfastleigh workshops. On 10th May 2012 the wheelsets sit waiting for movement to Llangollen after the tyres were fitted and profiled. The cranks have also been quartered. The balance weights will need to be adjusted after the wheels return to Llangollen to bring them into line for use under a ‘Grange’ Class locomotive.

It is expected that the VAB will inspect the work before transport to Llangollen shortly.

 

TRAIN TIMES FOR SSS3

Advance Ticket Sales going well

The advance ticket sales for SSS3 are progressing well and are substantially higher than figures for SSS2.

The souvenir brochure and timetable will be distributed to those who have ordered it later next week.

Engineering Progress

Progress on building 6880 is continuing as the following photographs show.

These bolts are for fixing the Extension Frames to the Main Frames

This is one of the Brake Shaft Castings

This is a view of the front end showing the cast brackets to support the front buffer beam

The footplating has been secured to the frames and painted

SSS3 Newsletter

Click here to view the SSS3 Newsletter now being sent to thousands of people across the UK  SSS3 Newsletter

Members gather at AGM

More than 40 members attended the AGM held at the Hand Hotel Llangollen on Saturday 28th January.

Members endorsed the progress made with plans for SSS3 and the general work done in the construction of No. 6880.

Afterwards a photograph was taken by David Wilcocks showing members in front of the locomotive for a local prestige glossy magazine publicising our project to a wider audience.

 

New SSS3 T Shirt

Our new SSS3 designer T shirt is now available for purchase.

Click this link to our Merchandise shop

http://www.6880.co.uk/6880-shop/merchandise

Tracklaying towards Bonwm

The Llangollen Railway volunteers are making good progress extending the line westwards towards Corwen. The expectation is to have trains running as far as Bonwm Halt in time for Steel, Steam & Stars III.

We expect to run the Autotrain down the extension starting from Glyndyfrdwy