A first coat of green undercoat has been applied as a visible step forward towards completion
Most of the pipe work and cab fittings are now in place as work progresses. We expect 6880 to steam this year
Work advances as the cladding and cleating are added along with the final fitting of the back head fittings. The locomotive edging ever nearer to completion
as the locomotive gets ever nearer to completion the lagging is being added to the boiler. Once complete the cladding can be fitted
The newly finished outer steam covers have been fitted for the first time bringing completion ever nearer
work continues on the small parts needed to finish the locomotive
The vacuum ejector pipe has been fitted along with the hand rail fittings there is a new smokebox dart and the steam pipes are now fixed
PHOTO SHOOT AT TYSELEY
An arranged photoshoot at Tyseley for Trackside magazine saw the temporary fitting of the steam pipes, chimney and safety valve cover. The locomotive was drawn out into the sunshine so the photos could be taken by a professional photographer. one photo appeared on the front cover and several were used in the multi page article. it is hoped to raise the Society profile and attract new members.
26th February saw a good turnout of members for the AGM. The locomotive is nearing completion and members were able to inspect progress first hand
Over the Christmas holiday period more pipe work has been added to the cab fittings including the condenser coil and the driving wheel sanding pipes. Attention is next turning towards the smoke box