Boiler

Boiler Trial Fitted

The boiler has been trial fitted into the locomotive to determine clearances and any other work needed before the tubes are fitted and an hydraulic test carried out. The work on the firebox is complete and the front taper section has been bolted on. The smoke box will be connected too before further work takes place.

Boiler Front Taper section

The front taper section with the front tube plate has been fitted to the rest of the boiler and firebox at Tyseley.

The next job will be to fit the tubes

Latest news from Tyseley

work continues on the boiler with the new front tube plate now fitted to the new front boiler section. Work finishing the firebox stays has also been completed. Finally work on the vacuum pump is being untaken to refurbish it.

Vacuum Pump

Vacuum Pump Piston

 

 

Progress at Tyseley

Much of the firebox is complete now with a large number of the stays added. The reamainder will be fitted within the next week or so. These views show the quality of workmanship being achieved. It’s easy to see where the money goes in refurbishing the boiler to such a high standard.

The smoke box awaits fitting.

the locomotive sits outside temporarily whilst awaiting the wheel drop to sort out a few issues with frame rivets.

Boiler work at Tyseley nearing completion

a visit to Tyseley locomotive works a few days ago revealed the huge progress made with our boiler. The back head now complete, the new boiler ring ready to be fitted and the smoke box ring now fitted to the smoke box. All looks on course for completion as planned by the end of June.

In addition the steam fountain was nearing completion and the safety valve was being machined.

Boiler update at Tyseley

work continues at Tyseley where the rivet holes for connecting the back plate to the foundation ring were being drilled. We also saw an unusual view of the firebox rear with both inner and outer back plates removed. The new front boiler ring has now arrived on site and is available for fitting when required.

Progress on boiler work at Tyseley

work on the boiler continues on schedule for completion this Spring. The new firebox lower outer sheets are ready to be welded in. Meanwhile two new throat plates have been made for both 4936 and 6880, ready to be riveted in once the outer sheets are finished. Outside the new smoke box barrel has arrived ready to be fitted once the new front boiler barrel arrives. Also on site is the metalwork for the new ashpan.

Boiler Work at Tyseley

Boiler work continues at Tyseley with the formation of a new front Tubeplate. The back head sheet has been removed for inspection and found to be in good condition for its age.

Boiler for 6880 at Tyseley

two views taken by Quentin this week of the boiler in Tyseley locomotive works ready for work to commence. Work is due to be finished by Spring 2018

More progress for Tyseley open day

Again more progress on the fitting of the Boiler Barrel Cladding Sheets, including boiler bands in place. Painting progress in the cab for the Reverser Stand and Sanding Gear Operating levers. Thanks as ever to Chris and all the Working Volunteers for the superb efforts over the 3 days